Do you have any questions? Call us! +36209594373

Installation

🏗️ INSTALLATION – How is a mobile home placed on-site?

After transportation, the mobile home is lifted from the transport vehicle using a heavy-duty crane and placed onto the pre-prepared foundation.


📍 What is required for on-site crane placement?

  • A flat, stable area of sufficient size for the crane and delivery truck (either on-site or on the adjacent street)

  • Solid ground or pavement for proper crane stabilization (outrigger setup)

  • The home is secured to the foundation using bolts, steel connectors, or welding



💧 UTILITY CONNECTION – Water, sewage, and electricity

Utility connections are typically completed before or during the installation process.



💦 WATER & SEWAGE CONNECTION

1. Permit application:

  • Water and sewage connection requests must be submitted to local providers

  • If no public sewage system is available: installation of a licensed septic tank or treatment unit is required

2. Identifying the connection points:

  • Water: public line or meter chamber at the property boundary

  • Sewage: municipal system or private holding tank

3. Infrastructure installation:

  • Water pipes: minimum 1.5 m below ground (frost protection), with shut-off and backflow valves

  • Sewage: 1.5% minimum slope, using PVC or KG-PVC pipes

4. Connecting to the building:

  • Internal plumbing is connected to the external network

  • After pressure testing and inspection, the system is ready for use

👷 Required professionals:

  • Licensed plumber

  • Excavator or earthwork specialist

  • Engineer (if utility upgrades are required)



⚡ ELECTRICAL CONNECTION

1. Authorization:

  • Electrical connection permit from the local power provider

  • Capacity request and meter installation (for new connections)

2. Connection point setup:

  • Existing network: pole or cabinet at property boundary

  • No network: new pole or underground cable is required

3. Installation:

  • Ground cable or overhead line installation

  • Installation of meter, fuses, FI-relay, grounding system

4. Final connection:

  • Cable is connected to the building’s internal distribution board

  • Electrical safety inspection and documentation are required

👷 Required professionals:

  • Licensed electrician

  • Certified network technician

  • Excavation crew (if underground cabling is needed)



🌄 SITE CONDITIONS – What kind of terrain is suitable for installation?

Installation is always based on a geotechnical report, which considers:

  • Soil bearing capacity

  • Slope and terrain profile

  • Rainwater drainage requirements



🛠️ For sloped terrain:

  • Drainage solutions (e.g. gravel trench, perforated pipe, open channel) may be needed

  • Protection against erosion or soil displacement is essential

🏖️ For sandy soil or waterfront plots:

  • Special foundations (e.g. ground screws, bored piles, or beam grids) are recommended



🛣️ HARD-TO-ACCESS LOCATIONS – Can a crane still be used?

Yes. Cranes can place buildings even in tight, sloped, or hard-to-reach areas, depending on weight and distance.



🏗️ Typical crane lifting specs (general reference):

Boom length Maximum lifting capacity
20 m ~ 4–8 tons
30 m ~ 2–4 tons
40 m ~ 1–2 tons
50 m ~ 0.5–1.5 tons


👉 Exact capacity depends on crane type and boom configuration



📐 Minimum requirements for safe crane setup:

  • Outrigger width: 1–4 meters

  • Lifting range: typically 15–50 meters (up to 80 meters in special cases)

  • Crane must be stabilized on solid, level surface